May 9, 2020 update: The Community Room remodeling project is almost complete with the installation of the tile. New window treatments, also known as blinds, will be installed in the coming weeks.

Main area

 

Table area

 

Serving area floor

 

Closeup of wood flooring and tile

 

 

May 2, 2020 update: The Community Room remodeling is going on as planned. The new wood flooring is complete. Vince has painted the cabinets and closets. The table where the coffee and donuts will be served is almost completed as well. The new window treatments and tile will be installed in the coming weeks.